WELLS NUMBER 27 AND 28 EQUIPPING
WELLS NO. 27 & 28 EQUIPPING
JURUPA COMMUNITY SERVICES DISTRICT
This is the first ASR (Aquifer Storage & Recovery) project for the district. Through the use of downhole control valves, the district will be able to replenish their groundwater aquifer through their groundwater extraction wells when system demand is low.
The project consisted of equipping of two (2) groundwater wells with 800hp pumps, VFDs, SCADA integration, standby diesel generators, CMU chemical and electrical building, on-site sodium hypochlorite generating systems, perimeter walls and fencing, and site improvements.
Owner: Jurupa Community Services District
Engineer/Construction Manager: Albert A. Webb & Associates
Contract Value: $7.1 Million